单选题

Earned value management(EVM)integrates the scope baseline with the(  )baseline, along with schedule baseline,to form the performance baseline,which helps the project management team assess and measure project performance and progress.

A

quality  

B

risk    

C

change    

D

cost

查看答案
答案
正确答案:D
解析

挣值管理(EVM)将范围基线与(成本)基线以及进度基线结合起来,形成绩效基线,帮助项目管理团队评估和衡量项目绩效和进度。

A.  质量

B.  风险

C.  变更

D.  成本